PROJECTS HISTORY — 2012 onward Completed and Running

BOROUGE – 3 U&O / XLPE – PROJECT – RUWAIS.

  • HYUNDAI E&C.
  • DAEYOUNG EMIRATES LLC.
  • NASSER SAEED ALHAJRI & PARTNERS.
  • INTHER PRO LLC.
  • AL HASON SEJONG E&M CO.
  • AL PINE BAU DEUTSCHLAND AG.
  • CAPE EAST LTD.
  • DESCON ENGINEERING & CONSTRUCTION CO.
  • GUSAN CONSTRUCTION CO.
  • KENTECH INTERNATIONAL LLC.
  • LARSON & TOUBRO LTD
Borouge 3 Plant - Ruwais Abu Dhabi

FERTIL 2 – AMMONIA & UREA PROJECT – RUWAIS.

  • PETROFAC.
  • SCADA SYSTEM.
  • AL HASON SEJONG M&E.
  • GUSAN CONSTRUCTION CO.
  • KENTECH INTERNATIONAL CO.
  • ARABIAN CONTRACTING CO.
  • AMANA CONT. & STEEL BUILDING.
  • CHINA PETROLEUM.
  • FOUR QUEST ENERGY.
  • IWI
Fertil Plant - Ruwais Industries - Abu Dhabi

AL HOSN SHA GAS – HAMEEM – ABU DHABI

  • AL HASON SEJONG E&M CO.
  • DESCON ENGINEERING & CONSTRUCTION CO.
  • DANWAY E&M CO.
  • INTHER PRO LLC.
  • KENTECH INTERNATIONAL LLC.
  • SCADA SYSTEM.
  • TARGET ENGINEERING CO.
  • NAFALCO OIL & GAS SERVICES
Alhason Gas Plant Sha Hameem

BARAKA NUCLEAR POWER PROJECT – BNPP – BARAKA [BNPP-PROJECT].

  • GUSAN CONSTRUCTION CO.
  • SEOBON CONSTRUCTION CO.
  • SHINWO CORPORATION.
  • HANLIM ENGG & CONS. CO.
  • AL HASON SEJONG E&M.
  • MULTIPLEX SERVICES.
  • SHIN KWANG CONTRACTING LLC.
  • YOUNCHANG ENGINEERING CO.
  • DOW INDUSTRIES LLC.
  • GULF PRECAST CONTRACTING.
  • NATIONAL MARING & DREDGING CO.
BARAKA NUCLEAR POWER PROJECT – BNPP – BARAKA

INDEPENDENT WATER POWER PROJECT – [IWPP] MIRFA.

  • HYUNDAI E&C.
  • GUSAN CONTRACTION CO.
  • SEOBON CONSTRUCTION CO.
  • WOOJIN MECH & ENGINEERING CO.
  • FICC CONTRACTING CO.
  • AL HUSAM GEN CONTRACTING CO.
  • NATIONAL PAINTING & CONTRACTING CO.
  • KINDLE STEEL & CONTRACTING CO.
INDEPENDENT WATER POWER PROJECT – [IWPP] MIRFA

ADNOC – GAS PROCESSING PROJECT – GASCO RUWAIS PROJECT:

  • AMANA CONT. & STEEL BUILDING CONTRACTING CO.
  • DESCON ENGINEERING CO.
  • AL HASSAN ENGINEERING CO.
  • ENGINEERING KENTECH LTD.
  • CONTROL & APPLICATION.
  • EMIRATES INDUSTRIAL LAB – EIL.
  • ISCCO
  • EKL CONTRACTING.
  • EMDAD SERVICES.
ADNOC - GAS PROCESSING PROJECT - GASCO RUWAIS

ADNOC – GAS PROCESSING PROJECT – GASCO HABSHAN PROJECT:

  • GUSAN CONSTRUCTION CO.
  • HYDONG E&C.
  • DESCON ENGINEERING CO.
  • STECON ELECTROMECHANICAL & CONTRACTING.
  • NATIONAL PAINTING & CONTRACTING CO. NPCC.
  • CONSOLIDATED CONTRACTING CO -(ccc)
  • EMDAD SERVICES LLC.
ADNOC - GAS PROCESSING PROJECT - GASCO HABSHAN

ADNOC – GAS PROCESSING PROJECT – GASCO ASAB PROJECT:

  • NATIONAL CONTRACTING CO.
  • EMDAD SERVICES.
  • DESCON ENGINEERING CO.
  • CEGELEC – ACTIMUM.
  • GRANITE CONSTRUCTION CO

 

ADNOC - GAS PROCESSING PROJECT - GASCO ASAB

RUWAIS OIL REFINERY PROJECT [TAKREER] – RRE / CBDC / RRW / CFP & WHRP – RUWAIS.

  • DAEWO E&C.
  • EMIRATESINDUSTRIALLAB–EIL.
  • ENGINEERINGKENTECHLIMITED.
  • INTHER PRO LLC.

 

  • SAMSUNG E&C.
  • DANWAY M&E.
  • AMEM INTERNATIONAL

 

  • TAHTAN GEN CONTRACTING CO LLC.
  • INECO.
  • INTHER PRO LLC.
  • AMB HERTIL.
  • BELLILI ENERGY.

 

  • SUNGBO E&C.
  • NASSER SAEED ALHAJRI & PARTNERS.
  • CONTRACTING CO.
  • BIN HAM ELECTROMECHANICAL & CONTRACTING.
  • GUSAN CONSTRUCTION CO.
  • DAESUN E&M CO.

 

  • SUNGDO E&C.
  • KINDLE STEEL CONSTRUCTION & CONTRACTING.
  • AL NASIR GENERAL CONTRING CO.
  • DESCON ENGINEERING CO.

 

  • AL DHAFIR TECHNIALOGIES.
  • TARGET ENGINEERING CO.
  • TAHTAN GENERAL CONTRACTING CO.
  • GULF REINFORCED PLASTIC LLC
TAKREER OIL REFINERY RUWAIS - ADNOC
TAKREER OIL REFINERY RUWAIS - ADNOC
TAKREER OIL REFINERY RUWAIS - ADNOC

Short term Projects – Shutdowns in different oilfields accomplished by Juma Khalfan Transport Passenger by buses leased.

  • Doosan Bobcock General Maintenance Services LC–Shutdown Job at Takreer Oil Refinery Ruwais from September 2016 to December 2016, with a fleet of 6 buses with drivers.
  • ISCCO–Shutdown Job at Gasco Ruwais Site from January 2016 to May 2016 with a fleet of 11 buses with drivers.
  • Emdad Services LLC–shutdown work at Fertil Ruwais site from October 2017 to December 2017 with a fleet of 5 buses with drivers.
  • Qatar Construction Co–shutdown work at Takreer Oil Refinery Ruwais from December 2016 to April 2016 with a fleet of 12 buses with drivers.
  • Descon Engineering Co–shutdown Job at Borouge Ruwais Site from January 2017 to April 2017 with a fleet of 12 buses without drivers.
  • Cape East Ltd–Shutdown work at Gasco Habshan Site from September 2017 to December 2017 with a fleet of 2 buses with drivers.
  • Doosan Bobcock General Maintenance Services LLC–Shutdown Job at Gasco Habshan Site September 2017 to December 2017 with a fleetof5 buses with drivers.
  • Emdad Services LLC-shutdown job at ADGASD asIsland from January 2018 till May2018with a fleet of 5 buses with drivers.
  • Descon Engineering Co–shutdown work at Borouge Ruwais site from February 2018 till April 2018.
  • Cape East Ltd–Shutdown work at Gasco Habshan Site September 2017 to December 2017 with a fleet of 2 buses with drivers.
  • Doosan Bobcock General Maintenance Services LLC–Shutdown Job at Gasco Habshan Site September 2017 to December 2017 with a fleetof5 buses with drivers.
  • EmdadServicesLLC-shut down job at ADGASD isIsland from January 2018 till May2018with a fleet of 5 buses with drivers.
  • Descon Engineering Co–shutdown work at Borouge Ruwais site from February 2018 till April 2018.
  • UTZ Kentz–shutdown works at Gasco Habshan Site from January 2018 till May 2018 with a fleet of 2 buses with drivers.
  • CAPE EAST LTD–shutdown Job at Alhason Gas Sha Plant from February 2018 upto 4months onward with a fleet of 2 buses with drivers.
  • EMCO– shutdown work at Al Hason Gas Sha Plant from November 2017 upto 6 months with a fleet of 2 buses with drivers.